#2026-393France updates grid connection rules for renewable energy in non-interconnected territories

🇫🇷France··Other·Medium Impact·View source ↗

AI-generated summary for informational purposes only. Not legal advice. See the original source for the authoritative text.

🇬🇧 English

This decree rewrites part of the Energy Code on how renewable electricity projects connect to public power grids in France’s non-interconnected territories, including Corsica, Guadeloupe, French Guiana, Martinique, Mayotte and Réunion. It clarifies which projects fall under renewable grid connection schemes, including certain waste-to-energy installations, and gives the public distribution network operator responsibility for preparing the connection scheme. Renewable power producers in these territories should watch the capacity-setting process, because the state representative will set the overall connection capacity after consultation with industry groups.

AI-generated summary. May contain errors. Refer to official sources for legal decisions.

Key Changes

  • Rewrites the Energy Code rules for renewable energy grid connection schemes in France’s non-interconnected territories.
  • Treats certain electricity generation from biodegradable waste as renewable generation for the full connection capacity of the installation.
  • Assigns the public distribution network operator to prepare the connection scheme, with the state representative setting total connection capacity after consultation.

Obligations

What this law requires

medium

Treat installations producing electricity wholly or partly from the biodegradable fraction of waste, including industrial waste and household or similar waste, as renewable electricity production installations for the full amount of their connection capacity when applying the renewable energy grid connection scheme.

public electricity distribution network operatorrenewable electricity project developers
operational
medium

Do not include in the renewable energy grid connection scheme installations whose connection conditions are set under Article L. 311-10, or renewable-fuel peak thermal installations operating less than 500 hours per year where connection financing is set under special procedures.

public electricity distribution network operatorelectricity project developers
operational
high

Prepare the renewable energy grid connection scheme for public electricity networks in Corsica, Guadeloupe, French Guiana, Martinique, Mayotte and Réunion.

public electricity distribution network operator
operational
medium

Before preparing the renewable energy grid connection scheme, inform the professional organisations of electricity producers and the State representative in the territory concerned.

public electricity distribution network operator
Before preparing the connection scheme
reporting
high

Submit a request to the State representative in the territory concerned to set the scheme’s overall connection capacity, and provide all necessary supporting elements, including estimates of total renewable electricity production capacity likely to request connection during the scheme period.

public electricity distribution network operator
reporting

Affected Parties

renewable electricity producers in Corsica and overseas non-interconnected territoriespublic electricity distribution network operators+2 more…

Tags

renewable energy,grid connection,non-interconnected territories