The Fenwick Solar Farm Order 2026 allows Fenwick Solar Project Limited to build and operate a large solar power station that will produce over 50 megawatts of electricity. This law enables the company to acquire land needed for the project, either by agreement or through compulsory means, affecting landowners and local communities.
AI-generated summary. May contain errors. Refer to official sources for legal decisions.
Key Changes
- Authorization for construction of a solar power station.
- Permission to acquire land for the project.
- Ability to operate and maintain the solar facility.
+ 1 more changes with Pro
Obligations
What this law requires
Fenwick Solar Project Limited must construct a ground mounted solar photovoltaic generating station with a gross electrical output capacity exceeding 50 megawatts in accordance with the terms of this Order
Fenwick Solar Project Limited must operate the solar photovoltaic generating station in accordance with the authorisation granted by this Order
Fenwick Solar Project Limited must maintain the solar photovoltaic generating station and associated development throughout its operational period
Fenwick Solar Project Limited must decommission the solar photovoltaic generating station at the end of its operational life in accordance with the terms of this Order
Fenwick Solar Project Limited is authorised to acquire land and rights in land needed for the project either by agreement with landowners or through compulsory acquisition procedures