Boott Hydropower LLC: Revised Procedural Schedule for Lowell Hydroelectric Project Relicense Application

🇺🇸United States··Notice·Low Impact·View source ↗

AI-generated summary for informational purposes only. Not legal advice. See the original source for the authoritative text.

🇬🇧 English

The Federal Energy Regulatory Commission (FERC) has issued a notice revising the procedural schedule for processing the major license renewal application filed by Boott Hydropower, LLC for the Lowell Hydroelectric Project (Project No. 2790), a 15.012-megawatt facility. The original relicense application was submitted on April 30, 2021, and an amendment was filed on June 20, 2025. Following the July 14, 2025 Notice of Material Amendment, FERC had anticipated issuing a 'Ready for Environmental Analysis' notice by March 2026. This updated notice pushes that milestone back to May 2026, reflecting a two-month delay in the environmental review process. The revision is administrative in nature and does not alter the substantive requirements of the relicense application. Further schedule adjustments may be made as circumstances warrant. Inquiries can be directed to FERC contact Bill Connelly at (202) 502-8587 or william.connelly@ferc.gov.

AI-generated summary. May contain errors. Refer to official sources for legal decisions.

Key Changes

  • Ready for Environmental Analysis notice deadline shifted from March 2026 to May 2026 (2-month delay)
  • Original relicense application filed April 30, 2021 for 15.012 MW Lowell Hydroelectric Project No. 2790
  • Material amendment to license application filed June 20, 2025

+ 2 more changes with Pro

Obligations

What this law requires

high

Boott Hydropower, LLC must ensure the Lowell Hydroelectric Project (Project No. 2790) relicense application complies with all substantive requirements of the major license renewal process

Boott Hydropower, LLC
licensing
high

Boott Hydropower, LLC must await FERC's 'Ready for Environmental Analysis' notice, now scheduled for May 2026, before proceeding to the environmental analysis phase

Boott Hydropower, LLC
operational
high

FERC must issue a notice that the Lowell Hydroelectric Project application is Ready for Environmental Analysis by May 2026

Federal Energy Regulatory Commission (FERC)
reporting
medium

FERC may make further revisions to the procedural schedule as circumstances warrant and must communicate any such revisions