#62025CC0539AG Opinion in Aquind v ACER on electricity interconnector exemption risk under Regulation 714/2009

European UnionOtherMedium ImpactView source ↗

This is an Advocate General’s opinion of 12 November 2026 in Case C-539/25 P, concerning Aquind Ltd’s appeal against the General Court judgment of 11 June 2025. The dispute centers on Article 17(1)(b) of Regulation (EC) No 714/2009, which allows an exemption for a new direct current interconnector only if the investment risk is so high that the project would not proceed without the exemption. The opinion discusses how national-law restrictions should be treated when assessing that risk and contrasts the exemption regime with the general cross-border cost allocation regime in Article 12 of Regulation (EU) No 347/2013. The case affects project promoters, national regulatory authorities, and ACER, especially for interconnector financing decisions and regulatory timetables.

AI-generated summary. It may contain errors and is not legal advice. For the authoritative text, see the official source.

Key Changes

  • The opinion focuses on Article 17(1)(b) of Regulation (EC) No 714/2009 and the requirement that the investment risk must be high enough that the interconnector would not be built without an exemption.
  • It addresses whether restrictions under French law can count as the kind of risk relevant to the Article 17 exemption assessment.
  • It distinguishes the Article 17 exemption regime from the ordinary cost-allocation mechanism in Article 12 of Regulation (EU) No 347/2013 for projects of common interest.
See 3 more changes with Pro

Affected Parties

  • Electricity interconnector developers and project promoters
  • National regulatory authorities in Member States
  • +3 more

Tags

electricity interconnector · ACER · Regulation 714/2009 · +3