This 15 October 2026 Court of Justice judgment interprets Article 35 of Directive 2012/34/EU on railway performance schemes, together with Article 56 and Annex VI, point 2. It concerns Italian rules under which RFI and the Transport Regulatory Authority (ART) applied two penalty regimes: a general delay scheme on the national network and a specific scheme for exceeding stop times at stations connecting with foreign rail networks. The Court addressed whether multiple penalty schemes may be combined and stressed that any scheme must respect the basic principles in Annex VI, including agreed main parameters, delay values, thresholds, and at least five days’ notice of the working timetable. The ruling affects infrastructure managers, railway undertakings, and national regulators, and it follows a preliminary reference made by the Consiglio di Stato on 18 February 2025, received by the Court on 24 February 2025.

AI-generated summary. It may contain errors and is not legal advice. For the authoritative text, see the official source.

Key Changes

  • The Court confirmed that Article 35(1) of Directive 2012/34 allows infrastructure charging schemes to include penalties, compensation, and bonuses, but only within a performance scheme designed to minimise disruption and improve network performance.
  • The Court held that Article 35(2) and Annex VI, point 2 require the basic principles of the performance scheme to apply throughout the network, including agreed main parameters, the value of delays, and payment thresholds for both individual train runs and the railway undertaking's total runs in a given period.
  • The Court examined a national model with a general delay penalty regime across the entire network and a separate regime for exceeding stop times at stations connecting with foreign rail networks, where the second regime targeted only railway undertakings.
See 2 more changes with Pro

Affected Parties

  • Railway infrastructure managers
  • Rail freight operators
  • +3 more

Tags

rail transport · performance scheme · network statement · +3

Related regulations

European Union