Energy

#2026-336France orders EDF to dismantle the Fessenheim nuclear power plant

🇫🇷France··Other·Medium Impact·View source ↗

AI-generated summary for informational purposes only. Not legal advice. See the original source for the authoritative text.

🇬🇧 English

This decree orders Électricité de France to dismantle the Fessenheim nuclear power plant, including both reactor units, fuel buildings, auxiliary nuclear buildings, conventional facilities, storage areas, electrical works, effluent tanks, and shared buildings. Some conventional and administrative buildings may stay if they support the future reuse of the site. EDF must complete the dismantling by 30 June 2048. The work is split into four phases: electromechanical dismantling, cleanup of structures and soil, demolition of buildings to at least one meter below current ground level, and site rehabilitation. EDF must monitor safety, worker radiation exposure, waste management, effluent releases, water use, and the condition of soil and subsoil, and report progress at least once a year to the local Fessenheim information and monitoring commission.

AI-generated summary. May contain errors. Refer to official sources for legal decisions.

Key Changes

  • Requires EDF to dismantle the full Fessenheim nuclear installation, covering nuclear, conventional, storage, electrical, effluent, and shared facilities.
  • Sets a final completion deadline of 30 June 2048 and defines four work phases: dismantling, cleanup, demolition, and site rehabilitation.
  • Requires annual local reporting on progress, nuclear safety, radiation exposure, contractor oversight, waste handling, and soil and subsoil conditions.

Obligations

What this law requires

critical

Proceed with the dismantling of Basic Nuclear Installation No. 75, the Fessenheim nuclear power plant, in accordance with the decree and the dismantling dossier of 30 November 2020 as updated on 23 December 2021, 21 July 2023, and 31 January 2025.

Électricité de France as operator of Basic Nuclear Installation No. 75
No specific start deadline stated
operational
high

Include in the dismantling operations the whole installation perimeter, including the reactor buildings, fuel buildings, peripheral buildings, nuclear auxiliary building, conventional island, pumping station and water intake/discharge works, industrial and tertiary buildings, electrical works, storage and interim storage buildings and areas, effluent storage tanks, and common buildings. Conventional installations and administrative buildings may be retained only if useful for the selected site reconversion.

Électricité de France as operator of Basic Nuclear Installation No. 75
By completion of dismantling
operational
critical

Complete all dismantling operations for Basic Nuclear Installation No. 75 no later than 30 June 2048.

Électricité de France as operator of Basic Nuclear Installation No. 75
No later than 30 June 2048
operational
high

Carry out the dismantling through the required stages: electromechanical dismantling; cleanup of structures and soils; demolition of buildings to at least one metre below current ground level, except retained conventional or administrative buildings; and rehabilitation of the site.

Électricité de France as operator of Basic Nuclear Installation No. 75
By completion of dismantling
operational
critical

Perform the surveillance, maintenance, and upkeep operations necessary to keep the installation in a safe condition throughout the dismantling period.

Électricité de France as operator of Basic Nuclear Installation No. 75
Continuously during dismantling
operational

Affected Parties

Électricité de FranceFessenheim site workers and contractors+3 more…

Tags

nuclear decommissioning,Fessenheim,EDF