Regulation on zoning and permitting for wind and solar power plants in Turkey
This regulation, published in the Official Gazette on 24 July 2026 (No. 33319), sets the procedures for zoning, parcelation, building permits, occupancy permits, and workplace operating licenses for wind and solar electricity generation plants holding an EPDK pre-license or generation license. It assigns these processes to the Ministry of Energy and Natural Resources and requires compliance with planning hierarchies, technical reports, public notices, and appeal periods. The rule affects RES and GES projects, their license holders, planners, and permitting consultants, and it also links planning and permitting to the Ministry of Environment, Urbanization and Climate Change’s systems and standards. It enters into force on publication date unless a specific article provides otherwise; the text provided includes Articles 1 to 10 and begins Article 10(4), so the remainder is not visible here.
AI-generated summary. It may contain errors and is not legal advice. For the authoritative text, see the official source.
Key Changes
- Article 1 makes the regulation applicable to wind or solar power plants that hold an EPDK pre-license or generation license and covers zoning plan approval, parcelation plan approval, building permits, occupancy permits, and workplace opening permits.
- Article 4 requires planning work to be based on existing maps, geological and geotechnical reports, and institutional opinions, and it allows simultaneous preparation and approval of the master plan and implementation plan.
- Article 6 requires a Plan Transaction Number from the Ministry of Environment, Urbanization and Climate Change system before zoning plans or amendments can be approved.