FHWA notice of final agency actions for Florida S.R. 60 widening project
This Federal Highway Administration notice announces final agency actions for the State Road 60 project in Osceola County, Florida, covering a 19.3-mile segment from Prairie Lake Road to Florida's Turnpike. The project will widen the existing two-lane road to four lanes, improve horizontal curve geometry, and replace the bridge over Blanket Bay Slough. The notice is important because it starts the 23 U.S.C. 139(l)(1) judicial review clock: claims must be filed on or before January 28, 2027, unless a shorter statutory deadline applies. It also confirms that FDOT assumed environmental responsibilities under 23 U.S.C. 327, that the Type 2 Categorical Exclusion was approved on April 29, 2026, and that the FHWA/FDOT actions are final for NEPA, Section 4(f), CAA, CWA, ESA, and related approvals listed in the notice.
AI-generated summary. It may contain errors and is not legal advice. For the authoritative text, see the official source.
Key Changes
- FHWA announced final agency actions for the State Road 60 project covering a 19.3-mile corridor from Prairie Lake Road to Florida's Turnpike in Osceola County, Florida.
- The project will widen the existing two-lane roadway to four lanes, improve horizontal curve geometry, and replace the bridge over Blanket Bay Slough.
- Any claim for judicial review of the federal agency actions must be filed on or before January 28, 2027 under 23 U.S.C. 139(l)(1), unless a shorter statutory filing period applies.
Affected Parties
- Florida Department of Transportation (FDOT)
- Federal Highway Administration and other federal permitting agencies
- +3 more