Algonquin Gas Transmission, LLC: Notice of Revised Schedule for Environmental Review of the Cape Cod Canal Pipeline Relocation Project
AI-generated summary for informational purposes only. Not legal advice. See the original source for the authoritative text.
The Federal Energy Regulatory Commission (FERC) has updated the schedule for its environmental assessment of Algonquin Gas Transmission's Cape Cod Canal Pipeline Relocation Project. The original schedule called for issuance of the Environmental Assessment on April 17, 2026. Due to Algonquin's delay in submitting the horizontal directional drill assessment report and additional project siting information, FERC has moved the EA issuance date to May 29, 2026. The EA will be open for a 30-day public comment period. The 90-day Federal Authorization Decision Deadline for other federal and state agencies is now August 27, 2026.
AI-generated summary. May contain errors. Refer to official sources for legal decisions.
Key Changes
- EA issuance date revised from April 17, 2026 to May 29, 2026
- 90-day Federal Authorization Decision Deadline set for August 27, 2026
- 30-day public comment period following EA issuance
+ 3 more changes with Pro
Obligations
What this law requires
Issue the Environmental Assessment (EA) for the Cape Cod Canal Pipeline Relocation Project by May 29, 2026
Open the Environmental Assessment for a 30-day public comment period following issuance on May 29, 2026
Ensure all federal and state agencies responsible for federal authorizations complete their decisions by the 90-day Federal Authorization Decision Deadline of August 27, 2026
Notify relevant agencies if any schedule changes become necessary regarding the environmental review timeline
Submit the horizontal directional drill assessment report and additional project siting information to FERC prior to EA issuance