This is a Federal Energy Regulatory Commission notice on Eastern Shore Natural Gas Company’s application under sections 7(b) and 7(c) of the Natural Gas Act and Part 157, filed September 24, 2026 in Docket No. CP26-585-000. The proposal would add pipeline loops, replace two Tidewater Line segments, abandon about two miles of existing line, build a new North Bridgeville M&R Station, and add valve facilities in Pennsylvania, Delaware, Maryland, and related rights-of-way. The project is fully subscribed and is designed to deliver 15,800 dekatherms per day of incremental firm transportation service at negotiated rates, with an estimated cost of $75,130,000. Businesses and other stakeholders interested in the proceeding must file motions to intervene by 5:00 p.m. Eastern Time on October 26, 2026; environmental review milestones include a 90-day staff review window under 18 CFR 157.9 and a subsequent 90-day federal authorization completion period after issuance of the FEIS or EA.

AI-generated summary. It may contain errors and is not legal advice. For the authoritative text, see the official source.

Key Changes

  • Eastern Shore Natural Gas Company filed an application on September 24, 2026 under sections 7(b) and 7(c) of the Natural Gas Act and Part 157 in Docket No. CP26-585-000.
  • The Delmar Regional Enhancement Project would build the 2.55-mile Parkesburg-Daleville Loop in Chester County, Pennsylvania; replace two 6-inch Tidewater Line segments totaling about 1.6 miles with 16-inch pipeline in New Castle County, Delaware; build the 5.05-mile Harrington Loop in Kent County, Delaware; and build the 1.85-mile Barksdale Loop in Cecil County, Maryland.
  • The project would abandon in place or by removal approximately two miles of the Tidewater Line in New Castle County, Delaware, and remove the existing North Bridgeville M&R Station while constructing a new North Bridgeville M&R Station in Sussex County, Delaware.
See 2 more changes with Pro

Affected Parties

  • Natural gas pipeline companies
  • Local landowners and right-of-way holders
  • +3 more