This is a Federal Energy Regulatory Commission notice about Equitrans, L.P.’s request under blanket certificate authority to build the H-320 Pipeline Project in Harrison County, West Virginia. The project would construct about 4.91 miles of 12-inch-diameter pipeline and increase take-away capacity on Equitrans’ mainline system to serve a proposed Wolf Summit Energy, LLC power plant with 108,000 dekatherms per day of natural gas service. The estimated cost is $46,650,804, and the request was filed on October 28, 2026 in Docket No. CP27-10-000 under 18 CFR 157.205, 157.208(c), and 157.210, with blanket certificate authority originally in CP96-532-000. Protests, motions to intervene, and comments are due by 5:00 p.m. Eastern Time on January 8, 2027; timely, unopposed intervention is automatically granted under Rule 214(c)(1).

AI-generated summary. It may contain errors and is not legal advice. For the authoritative text, see the official source.

Key Changes

  • Equitrans seeks authorization under 18 CFR 157.205, 157.208(c), and 157.210 to construct approximately 4.91 miles of 12-inch pipeline called the H-320 Pipeline Project.
  • The project is intended to increase take-away capacity on Equitrans' mainline system and enable delivery of 108,000 dekatherms per day to a proposed Wolf Summit Energy, LLC power plant.
  • The estimated project cost is $46,650,804 and the request was filed on October 28, 2026 in Docket No. CP27-10-000.
See 2 more changes with Pro

Affected Parties

  • Natural gas pipeline operators
  • Power plant developers and prospective off-takers