FERC notice on GB Energy Park’s request to extend construction deadlines for the Gordon Butte Pumped Storage Project

United StatesNoticeLow ImpactView source ↗

This Federal Energy Regulatory Commission notice announces that GB Energy Park, LLC filed a request on August 31, 2026, to extend the construction deadlines for the licensed Gordon Butte Pumped Storage Project, Project No. 13642-003. The company asks to move the deadline to commence construction from December 14, 2026 to December 14, 2028, and the deadline to complete construction from December 14, 2029 to December 14, 2031, a two-year extension for each milestone under Article 301 of the license and Public Law 119-90, section 1020 (140 Stat. 820-21). Comments, protests, and motions to intervene are due by December 7, 2026 at 5:00 p.m. Eastern Time. The notice affects the applicant, FERC, potential intervenors, resource agencies, and any stakeholders in the Montana hydroelectric project review process.

AI-generated summary. It may contain errors and is not legal advice. For the authoritative text, see the official source.

Key Changes

  • GB Energy Park, LLC requested a two-year extension for the Gordon Butte Pumped Storage Project under Article 301 of the license.
  • The requested commencement deadline would move from December 14, 2026 to December 14, 2028.
  • The requested completion deadline would move from December 14, 2029 to December 14, 2031.
See 2 more changes with Pro

Affected Parties

  • GB Energy Park, LLC
  • Potential intervenors and protestors
  • +3 more

Tags

FERC · hydroelectric project · extension of time · +3