Environment

FERC notice of availability of environmental assessment for the Viola natural gas pipeline project

United StatesNoticeLow ImpactView source ↗

This Federal Energy Regulatory Commission notice announces the availability of the environmental assessment for Southern Star Central Gas Pipeline, Inc.'s Viola Project in Docket No. CP26-74-000. The proposal would add a new meter station, flow station, compressor station, and 19.3 miles of 16-inch natural gas pipeline in Sumner County, Kansas, to serve up to 116,296 dekatherms per day for Evergy's planned 710-megawatt Viola Plant. FERC says comments on the EA must be received by 5:00 p.m. Eastern Time on November 9, 2026, and explains that the EA is not a decision document. The notice is procedural and environmental in nature, and it affects the project sponsor, affected landowners, tribes, agencies, and other stakeholders in the project area.

AI-generated summary. It may contain errors and is not legal advice. For the authoritative text, see the official source.

Key Changes

  • FERC has made the environmental assessment for the Viola Project available for public review in Docket No. CP26-74-000.
  • Southern Star is seeking authorization for 19.3 miles of new 16-inch-diameter Line UA pipeline, a new meter station, a flow station, and a compressor station in Sumner County, Kansas.
  • The project is designed to deliver up to 116,296 dekatherms per day of natural gas to Evergy's planned 710-megawatt Viola Plant.
See 2 more changes with Pro

Affected Parties

  • Southern Star Central Gas Pipeline, Inc.
  • Evergy, Inc. and the planned Viola Plant
  • +3 more

Tags

FERC · environmental assessment · natural gas pipeline · +3

Related regulations

United States