FERC Combined Notice of Filings 1 (March 2026)
AI-generated summary for informational purposes only. Not legal advice. See the original source for the authoritative text.
The U.S. Federal Energy Regulatory Commission (FERC) published a combined notice on March 31, 2026, listing multiple regulatory filings received between March 25-26, 2026. The notice covers accounting entries for a completed transaction by PECO Energy Company, self-certifications of Exempt Wholesale Generator status by two solar-related LLCs, and numerous electric rate and tariff filings. These include compliance informational filings under PJM OATT Schedule 2, multiple Market-Based Rate (MBR) tariff submissions, several §205 rate filings by utilities and RTOs such as PacifiCorp, PJM, MISO, and Tri-State, as well as amendments to interconnection agreements and service contracts. Most filings have a comment deadline of 5:00 p.m. ET on April 15 or 16, 2026.
AI-generated summary. May contain errors. Refer to official sources for legal decisions.
Key Changes
- PECO Energy Company submitted final accounting entries for a transaction with Calpine Mid Merit, LLC consummated on December 3, 2025
- Two new self-certifications of Exempt Wholesale Generator status: 45MG 8me LLC and 301AK 8me LLC, filed March 26, 2026
- Multiple §205(d) rate filings with effective dates ranging from March 1, 2026 to June 1, 2026
+ 3 more changes with Pro
Obligations
What this law requires
PECO Energy Company must submit final proposed accounting entries for the transaction consummated on 12/03/2025 with Calpine Mid Merit, LLC to FERC in Docket AC26-34-000 (Accession 20260326-5221)
45MG 8me LLC must file Notice of Self-Certification of Exempt Wholesale Generator Status with FERC in Docket EG26-187-000 (Accession 20260326-5169)
301AK 8me LLC must file Notice of Self-Certification of Exempt Wholesale Generator Status with FERC in Docket EG26-188-000 (Accession 20260326-5172)
Lackawanna Energy Center LLC must submit compliance informational filing pursuant to Schedule 2 of PJM OATT in Docket ER18-2370-006 by comment deadline of 5:00 p.m. ET on 4/16/26
All entities submitting §205(d) rate filings (including PacifiCorp, Salem VA BESS 1 LLC, Colleen VA BESS 1 LLC, Meadow Creek VA BESS 1 LLC, Piney River VA BESS 1 LLC, and others) must ensure tariff filings are submitted with specified effective dates and subject to FERC comment periods ending 5:00 p.m. ET on 4/15-4/16/26