Algonquin Gas Transmission, LLC: Notice of Revised Schedule for Environmental Review of the Cape Cod Canal Pipeline Relocation Project

🇺🇸United States··Notice·Medium Impact·View source ↗

AI-generated summary for informational purposes only. Not legal advice. See the original source for the authoritative text.

🇬🇧 English

The Federal Energy Regulatory Commission (FERC) has updated the schedule for its environmental assessment of Algonquin Gas Transmission's Cape Cod Canal Pipeline Relocation Project. The original schedule called for issuance of the Environmental Assessment on April 17, 2026. Due to Algonquin's delay in submitting the horizontal directional drill assessment report and additional project siting information, FERC has moved the EA issuance date to May 29, 2026. The EA will be open for a 30-day public comment period. The 90-day Federal Authorization Decision Deadline for other federal and state agencies is now August 27, 2026.

AI-generated summary. May contain errors. Refer to official sources for legal decisions.

Key Changes

  • EA issuance date revised from April 17, 2026 to May 29, 2026
  • 90-day Federal Authorization Decision Deadline set for August 27, 2026
  • 30-day public comment period following EA issuance

+ 3 more changes with Pro

Obligations

What this law requires

high

Issue the Environmental Assessment (EA) for the Cape Cod Canal Pipeline Relocation Project by May 29, 2026

Federal Energy Regulatory Commission (FERC) staff
operational
high

Open the Environmental Assessment for a 30-day public comment period following issuance on May 29, 2026

Federal Energy Regulatory Commission (FERC) staff
disclosure
high

Ensure all federal and state agencies responsible for federal authorizations complete their decisions by the 90-day Federal Authorization Decision Deadline of August 27, 2026

Federal agencies and state agencies acting under federally delegated authority
operational
medium

Notify relevant agencies if any schedule changes become necessary regarding the environmental review timeline

Federal Energy Regulatory Commission (FERC) staff
disclosure
high

Submit the horizontal directional drill assessment report and additional project siting information to FERC prior to EA issuance

Algonquin Gas Transmission, LLC
reporting

Affected Parties

Algonquin Gas Transmission, LLCFederal and state permitting agencies+3 more…

Tags

FERC,environmental assessment,pipeline relocation