FERC Sets Environmental Review Schedule for Constitution Pipeline and Wright Interconnect Projects
AI-generated summary for informational purposes only. Not legal advice. See the original source for the authoritative text.
FERC is preparing an environmental assessment for two revived natural gas infrastructure projects: the Constitution Pipeline and the Wright Interconnect. The projects would add about 125 miles of 30-inch natural gas pipeline across parts of Pennsylvania and New York, plus new and expanded compressor and metering facilities. The notice sets the review timetable. FERC plans to issue the environmental assessment for public comment on August 21, 2026, with a federal authorization decision deadline of November 19, 2026. Energy companies, local governments, landowners, environmental groups, and communities along the route should watch the comment period and prepare input if they may be affected.
AI-generated summary. May contain errors. Refer to official sources for legal decisions.
Key Changes
- FERC will prepare an environmental assessment for the Constitution Pipeline and Wright Interconnect projects.
- The environmental assessment is scheduled for release for public comment on August 21, 2026.
- Federal authorization decisions are targeted by November 19, 2026.