This law pertains to the application filed by ALLETE, Inc. for the relicensing of the Pillager Hydroelectric Project located on the Crow Wing River in Minnesota. The application is for a new major license under the Federal Power Act and is currently available for public inspection. The project includes various facilities such as a reservoir, a dam, and a powerhouse, and it is proposed to operate in a run-of-river mode with substantial energy production.
AI-generated summary. May contain errors. Refer to official sources for legal decisions.
Key Changes
- Application for new major license for the hydroelectric project
- Public inspection availability of the application
- Proposed continuation of run-of-river operation mode
Obligations
What this law requires
ALLETE, Inc. must file final amendments to the application with the Federal Energy Regulatory Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis.
ALLETE, Inc. must make the hydroelectric relicensing application available for public inspection as filed with the Commission.
ALLETE, Inc. must respond to any Deficiency Letter issued by FERC by the target date of July 2026.
ALLETE, Inc. must respond to any Additional Information Requests issued by FERC by the target date of July 2026.
ALLETE, Inc. must operate the Pillager Hydroelectric Project in run-of-river mode as proposed in the relicensing application.